Overview
To keep projects on schedule and compliant during the SolarEdge Backup Interface (BUI) shortage, guidelines will be provided to allow conditional approval installation submitted (M1) while awaiting components. M1 packages can be submitted and approved with exceptions for BUI requirements, which are deferred to Activation package (M2), ensuring projects continue moving through the pipeline.
M1 Requirements
These guidelines allow conditional approval while awaiting components to keep projects on schedule and compliant while working through the SolarEdge shortage.
All requirements must be satisfied to achieve M1 conditional approval with the exception of all Balance of System (BOS) components installed up to the point of the back up interface including all roof photo requirements.
Follow the M1 checklist HERE which mirrors the review process for M1.
All BOS components installed up to the point of the back up interface must be installed with applicable photos for M1 conditional approval - examples of needed components below.
Inverter serial Label
RGM production meter
Battery Serial label
AC disconnect (if line diagram indicates AC disco on BOS side of BUI)**
BOS Pullback of equipment installed (excluding BUI)**
M2 Requirements
Activation Milestone (M2)requires full project completion, including backup interface installation and final interconnection.
Photos to be provided at M2 should be upload to the site improvement photos section. These photos include the following to be approved
Communication wire between BUI and inverter
Consumption CTs
Back up interface installed and wired
Complete BOS pullbacks with BUI installed
Interconnection of inverter into BUI
AC disconnect fully wired (applies only for fused disconnects)
BUI Seral label
Interconnection
Commissioning
Service panel Main breaker and Bus rating.