This article details our current incentives deliverables required at System Activation (M2) milestones on all LightReach sales.
Images linked below can be found here: Incentive Requirements Checklist . Submitting M1 documents without as-built information, or omitting documents altogether, will result in the rejection of the M2 milestone.
Requirements by State:
State | Document 1 | Document 2 |
Connecticut | PTO Letter | N/A |
New Jersey | Portal screenshot of | SREC-II Certification Letter once certification is obtained SREC-II Certification Letter |
Pennsylvania | Certificate of Completion (COC) | N/A |
Ohio | Certification of Completion (If Applicable) | N/A |
Maryland | Certificate of Completion (COC) | N/A |
Massachusetts | N/A | N/A |
DC | N/A | N/A |
Illinois
| COC/PTO Ameren - Ameren - PTO ComEd - ComEd - COC | Net Metering Approval Ameren - Ameren - NM ComEd - ComEd - NM |
California | N/A | N/A |
*IL - Ameren PTO letter will be the same document as the net metering approval document*