This guide walks through everything required to complete the Generator Install Package submission. It covers five components:
Install Package Documentation
Equipment & Site Photos
Installer Attestations
FieldPro Commissioning Screenshots
Customer Sign-Off
Installation Documents
Use the links and examples in this article to ensure your submission meets Palmetto's internal review standards.
Item | Deliverable |
Installation Contract or Work Order | Upload a copy of the signed installation contract or work order. The total cost of installation must be clearly stated and must equal the amount financed by Palmetto, ± $100. Deviations greater than $100 will be rejected pending clarification. |
New System Photos
Item | Deliverable |
Equipment Nameplate |
|
Cellular Device ID |
|
Wide / Pullback Shots of Generator (2–4 photos) |
|
ATS Close-Up (+ pullback if not co-located) |
|
Main Service Panel (Door Open Photo) |
|
Installer Attestations
The items below rely on installer attestation rather than a submitted document or photo. Palmetto reserves the right to request supporting documentation for QC audit.
Item | Deliverable |
Generator Sizing | Installer attests the generator is appropriately sized for backed-up loads, based on square footage. (Sizing tool used: PowerPlay at Generac.com or similar.) |
CO Detector(s) | Installer attests CO detectors are installed per local code, or per Generac installation requirements, and confirms the count installed. No photo required. |
No Conflicting Downstream Generation | Installer attests no downstream generation conflicts exist at the site — no solar, battery, or other generation source that could cause a parallel generation or backfeed conflict. |
Load Control Devices (SMMs) | Installer attests to the quantity of installed load control / smart management modules. Paired with a single pullback photo showing all installed devices. |
Permitting - One must be selected | Option A (Permit Obtained):
Click HereI confirm that all permits required by the applicable Authority Having Jurisdiction (AHJ) for this generator installation have been obtained. I further confirm that: (a) all required inspections have been completed and passed, and (b) a copy of the final inspection approval or closed permit is attached to this submission. If final inspection has not yet occurred, I have noted the scheduled inspection date in this submission and understand that final payment may be withheld until inspection approval is received by Palmetto.
Option B (No Permit Required):
Click HereI confirm that no permit or inspection is required by the applicable Authority Having Jurisdiction (AHJ) for this type of generator installation at this location. This determination is based on my direct verification with the AHJ, and not solely on past practice or assumption. I understand that if a permit is later determined to have been required, I am responsible for obtaining the permit retroactively at my own expense, and Palmetto reserves the right to withhold or reverse payment until permit compliance is confirmed. The installation has been performed in accordance with all applicable codes and manufacturer installation requirements.
|
Documentation Accuracy and Truthfulness |
Click HereI confirm that all photos, documents, screenshots, and information submitted in this installation package are true, accurate, and representative of the actual as-installed system at the property as of the date of this submission. I have not altered, staged, or misrepresented any submitted materials.
|
FieldPro Commissioning Screenshots
Mobile Link data alone is not sufficient for the items below — FieldPro screenshots are required.
Item | Deliverable |
Fuel Line Pressure Tests | FieldPro app screenshots must show a passing pressure reading. |
FieldPro Green Status (post-runtime) | A single screenshot showing all parameters green with no active alarms, captured after the generator has completed a 30-minute minimum (up to 1 hour) run, targeting 80% load capacity. |
Wi-Fi Connectivity Confirmed | A screenshot confirming Wi-Fi is connected and active at time of commissioning. (Wi-Fi is also visible in the fuel-pressure-test screenshots — this item is a deliberate double-check, since cellular activates at warranty registration and Wi-Fi is the preferred fail-safe for reliability.) |
Customer Sign-Off
Item | Deliverable |
Customer Walk-Through & Sign-Off | Installer attests the homeowner has completed a walk-through covering system operation, exercise schedule, maintenance expectations, and emergency procedures.
|







