The Loop Field milestone confirms that the underground geothermal loop field has been fully installed and verified before moving into indoor equipment installation. It is the first operational milestone. The Loop Field milestone is a two-part submission:
Part 1 - Design documents: submitted up front in the Design section of the portal.
Part 2 - Loop field package: the install-verification documents, submitted after the loop field is in the ground.
Both parts must be complete before the milestone can be approved. Submit everything through the Palmetto Portal or API.
Supported configurations
Loop field: closed-loop only, either vertical bore or horizontal trench
Indoor unit: forced-air (ducted)
Not supported in the initial version
Pond/lake loops
Hydronic/radiant indoor configurations
Retrofits and new construction (whole-system installs at existing homes only)
Requirements
| Manual J Load Calculation | Whole-house heating and cooling load calculation per ACCA Manual J, room-by-room.
|
2 | Manual S Equipment Selection | Heat pump selection report demonstrating capacity match to Manual J loads at design conditions.
|
3 | Ground Loop Design Report | Loop sizing and configuration from an accepted geothermal design tool.
|
Submitted after the loop field is installed. Provide all of the following:
1 | Permit | Approved permit, with the permit submitted date and approved date. The permit must be approved before the Loop Field milestone can be completed. |
2 | Pressure test results | Documentation of the loop pressure test. |
3 | Loop field photos | Clear installation photos (see the shot list below).
|
4 | Drilling invoice | Invoice from the driller for the loop field work. |
5 | Bore log / as-built | The as-built bore log showing actual bore depths and configuration. |
6 | Driller information | Driller name and license. |
How to submit the Loop Field package
How to submit the Loop Field package
Permit Approved
Permit Submitted Date / Approved Date
Driller Information
Driller Name
Driller License
Pressure Test Results
Loop Field Photos
Provide clear installation photos showing:Trenches or boreholes before backfill
Pipe placement and fusion joints
Headers and manifold connections
Grouting setup and completion