Clawbacks

Disclaimer: LightReach reserves the right to withhold or claw back funds in certain scenarios.

Clawback Extension Requests:

When project timelines are anticipated to surpass the standard 115-day completion period for a reason outside of the EPC's control, partners have the option to submit an extension request. Requests must be submitted through the installer support chat. Each request can include up to one account. If more than one project needs an extension, partners will need to submit multiple requests.

This process is a privilege earned not given, submitted requests must always have a valid reason accompanied by supporting documentation. Palmetto LightReach will evaluate each extension requests against any clawback extensions already granted and reserves the right to deny an extension request.

Please allow 1 week from submission to confirm if an extension request is approved or denied. If the request is approved and the clawback transaction is already populated on the account, this will be marked as "Paused" in the portal immediately. If the clawback transaction has not populated yet to the account, this will be paused prior to the following funding cycle. All accounts with approved requests are reviewed the day prior to each funding cycle (Monday / Wednesday) and any new clawback transactions will be paused during that time.

Reason

Timeline

PTO is approved and uploaded, Service delay correction M2 deliverables

14 Day Extension

Utility / AHJ delays outside of EPC control

30 Day Extension

CA/CO/GA: Market 30 day Extension (145 day Duration)

30 Day Extension

AEP - TX: Utility 30 day Extension

(145 day duration)

30 Day Extension

Other - Installer to Provide Reasoning within Submission

Determined Based on Circumstances

Total Extension Exposure:

  • Under no circumstance will Palmetto allow for more than [5% of Post Install not Activated Backlog OR $500k EXTENDED] at any given point

Email or Proof of delay must be uploaded in the account document section of the Palmetto Finco Portal (Supporting Document).

How to Submit a Clawback Extension Request:

Click here to instantly submit a Clawback Extension Request!

OR

Chat Selection Path: Installer: Admin Support > Funding Details > Clawback Extension Request.

Requests should include the following information:

  • Account Primary Name

  • Account Finco ID

  • Account Link

  • Install Payment (Batch) Date

  • Current PTO ETA (must be updated in the portal, can't be past due)

  • Extension Request Timeline (14 / 30 days)

  • Market (State)

  • Market (Utility)

  • Extension Reasoning (this should include the full project timeline from install)

  • Supporting Documentation (must be from AHJ / Utility if reason for delay)

Extensions are intended for delays that are outside the EPC’s reasonable control and can be verified with documentation from the AHJ or utility. The reasons below are considered part of the normal install-to-PTO process, or are within the EPC’s control, and will not qualify for a clawback extension on their own.

If a delay is already known at the time of install, such as an MPU, please keep your organization’s clawback terms in mind when deciding whether to submit M1 and be paid for the installation. Delays known or reasonably anticipated at the time of M1 submission generally do not qualify for an extension unless a new, independently qualifying event occurs.

Examples:

  • Known MPU requirement: An MPU identified before M1 submission does not automatically qualify.

  • Unexpected external delay: An unforeseen utility-related delay arising during MPU completion may qualify with appropriate documentation.

  • EPC scheduling delays: Delays resulting from the EPC’s failure to coordinate or schedule the MPU do not qualify on their own.

Reason Not Accepted

Details

Inspection, permit, and plan-related delays

Inspection corrections, re-inspections, permit revisions, and plan revisions. Inspection readiness, permit accuracy, resubmission and plan set changes are managed by the EPC.

Homeowner-related delays

Delays caused by homeowner scheduling, availability, or responsiveness are the EPC’s responsibility to manage.

Current project status only

A status update is not a reason for delay. Requests must identify the specific cause of delay, relevant dates, and supporting documentation.

Extension Review Requirements:

All extension requests must clearly demonstrate the qualifying cause of the delay, how it impacts the applicable milestone deadline, and the steps taken by the EPC to mitigate the impact.

Requests based solely on the reasons listed above, or submitted without sufficient supporting documentation, will not be approved.

Palmetto LightReach reserves the right to review and deny extension requests that do not meet established eligibility requirements.


​